Vestas hat einen Auftrag über 139 Windanlagen für E.ON Windpark in den USA erhalten

The order for 24 Vestas V110-2.0 MW wind turbines was placed by long-time customer China Longyuan Power Group Corporation. / Pressebild: Vestas

Vestas wird 139 V110-2.0 MW-Windanlagen mit insgesamt 278 MW liefern.

(WK-intern) – Der Auftrag umfasst die Lieferung und Inbetriebnahme der Windenergieanlagen, sowie eine mehrjährige Servicevereinbarung.

Vestas has received a firm and unconditional order in the USA comprising 139 V110-2.0 MW turbines, totalling 278 MW.

E.ON orders 139 V110-2.0 MW turbines.

With reference to Vestas Wind Systems A/S’ company announcement No. 24/2016 of 10 August 2016, Vestas has received a firm and unconditional order from E.ON for 139 V110-2.0 MW turbines.

“We are excited to be working with Vestas on this turbine purchase as E. ON expands its U.S. portfolio,” said Patrick Woodson, Chairman of E.ON North America.

The order includes supply and commissioning of the wind turbines as well as multi-year service agreement.  Nacelles, blades, and towers will be produced at Vestas’ Colorado factories with delivery expected to begin in the second quarter of 2017 and commissioning planned for the fourth quarter of 2017.

“We’re honored to build on our successful relationship with E.ON and further deploy the versatile V110-2.0 MW turbine to their project.  E.ON is a dedicated renewable energy leader both globally and in North America, and we look forward to help them deliver low-cost, clean electricity,” said Chris Brown, President of Vestas’ sales and service division in the United States and Canada.

Since the Vestas 2 MW-platform’s debut, more than 33 GW have been installed globally.

Additional information about the project:

Customer: E.ON
Project name: Undisclosed at the customer’s request
Location/Country: USA
Number of MW: 278 MW
Number of turbines/turbine type(s): 139 x V110-2.0 MW turbines
Contract type: Supply-only
Contract scope: The contract includes supply and commissioning of the wind turbines, as well as a multi-year service agreement.
Time of delivery: Delivery of the wind turbines is expected to begin in the second quarter of 2017, with commissioning expected in the fourth quarter of 2017.

Total year-to-date announced order intake in MW: 4,216 MW (see overview at vestas.com/investor).

About Vestas
Every single day, Vestas wind turbines deliver clean energy that supports the global fight against climate change. Wind power from Vestas’ more than 57,300 wind turbines currently reduces carbon emissions by over 82 million tons of carbon dioxide every year, while at the same time building energy security and independence. Vestas has delivered wind energy in 75 countries, providing jobs for around 21,500 passionate people at our service and project sites, research facilities, factories and offices all over the world. With 50 percent more megawatts installed than anyone else in the industry and over 75 GW of cumulative installed capacity worldwide, Vestas is the world leader in wind energy.

PR: Vestas Wind Systems A/S, Denmark

Pressebild: Vestas has received a firm and unconditional order in the USA comprising 139 V110-2.0 MW turbines, totalling 278 MW.

Weitere Beiträge:



Top