MHI Vestas Offshore Wind erhält 165 MW-Auftrag in Belgien

MHI Vestas Offshore Wind receives 165 MW order in Belgium / Pressebild: Vestas
MHI Vestas Offshore Wind receives 165 MW order in Belgium / Pressebild: Vestas
MHI Vestas Offshore Wind receives 165 MW order in Belgium / Pressebild: Vestas

MHI Vestas liefert 50 V112-3.3 MW-Turbinen für das 165 MW Nobelwind-Projekt vor der belgischen Küsten – das ist das dritte Vestas-Windprojekt

(WK-intern)MHI Vestas Offshore Wind wird 50 V112-3.3 MW-Turbinen für das 165-MW-Windkraftanlage Nobelwind in Belgien zu liefern.

Der Auftrag wurde von Nobelwind NV, einem belgischen Entwickler, Eigentümer und Betreiber der 165 MW und des 216 MW Belwind North Projekte unterzeichnet.

Das Nobelwind-Projekt wird auch einen 15 Jahre Servicevertrag mit MHI Vestas beinhalten.

MHI Vestas Offshore Wind receives 165 MW order in Belgium

Parkwind and MHI Vestas partner up for the supply of 50 V112-3.3 MW turbines for the 165 MW Nobelwind project off the Belgian coast- the third project between the two companies.

MHI Vestas Offshore Wind will supply 50 V112-3.3 MW turbines for the 165 MW Nobelwind wind power plant in Belgium. The order has been placed by Nobelwind NV, who signed up with Parkwind, a Belgian developer who owns and operates the 165 MW Belwind and 216 MW Northwind projects, together with reference shareholders Sumitomo Corporation and Meewind.

The Nobelwind project will also include a 15 year full-scope service contract with MHI Vestas, optimising the output of the wind power plant with guaranteed availability, while minimising risk for the customer.

CEO Jens Tommerup said, “We are proud that Parkwind has once again decided to partner with MHI Vestas to supply turbines for the Nobelwind project;” said Jens. And continues. “When the project is completed, MHI Vestas and Parkwind will have together installed over 500 MW in Belgium, with all projects serviced by MHI Vestas technicians working out of our site office in Oostende.”

The Nobelwind power plant is located 47km from the coast of Belgium in the North Sea. When completed in 2017 the project will produce 651 GWh of clean energy annually, enough to provide energy for over 186.000 Belgian households.